CDU Approach Temperature: Read the Capacity Rating

Learn what CDU approach temperature means, separate it from loop temperature rise, and compare capacity quotes using the same fluids and design conditions.

US Liquid Cooling editorial · Reviewed · 4 min read

A CDU's approach temperature describes how close the cooled technology-loop supply gets to the entering facility-side fluid temperature, using the manufacturer's stated measurement convention. A smaller approach can be valuable, but it is meaningful only alongside heat duty, fluid properties and flow conditions.

That is why two CDUs both advertised as “1 MW” are not automatically equivalent for a project with a tight temperature budget.

Name the temperatures before comparing them

In a common liquid-to-liquid arrangement, the facility loop removes heat from a separate technology cooling loop. The technology supply leaves the CDU toward the IT equipment. The facility supply enters the CDU from the building's heat-rejection system.

If those temperatures are 35°C and 30°C respectively, the cold-end difference is 5°C. Confirm that this is the convention used in the vendor's performance schedule; do not assume that every temperature labeled “delta T” refers to the same two sensors.

The technology loop might then return at 45°C. Its 10°C rise across the IT load is a different quantity from the 5°C approach at the heat exchanger.

Why does the capacity rating need conditions?

A heat exchanger's usable duty depends on the available temperature differences, flow and fluid properties. A nominal capacity detached from those conditions cannot establish whether the unit can maintain your required IT supply temperature.

Vertiv's CoolChip CDU 70 listing pairs its stated duty with an approach condition. The broader CoolChip CDU product range likewise lists product ratings under defined conditions.

Read the schedule behind the product name. A larger number on the enclosure is not evidence that the unit will provide the same duty at your warmer facility inlet or tighter required approach.

Put two offers on the same basis

Give both suppliers the same input schedule:

InputWhat the schedule should state
Heat dutyNormal, peak and required degraded-case duty
Facility supplyDesign and worst-case entering temperature
Technology supplyMaximum permitted temperature to the IT equipment
FluidsProduct, concentration and relevant properties on both sides
Flow and pressureAvailable facility flow, branch requirements and pressure limits
ResilienceWhich components remain available during the specified fault

Ask each supplier to return a selected operating point, approach definition, flow requirements, pressure drops and electrical consumption for that point. Keep exclusions visible, especially where facility pumping or external valves are outside the CDU quotation.

A small difference can consume a temperature budget

Imagine IT equipment that permits 40°C inlet coolant and a facility supply of 35°C. Before allowing for distribution effects or margin, the simple temperature budget is 5°C. A proposal requiring a 10°C approach at the necessary duty would not meet that stated combination.

Possible responses include a different heat exchanger selection, more suitable flows, a cooler facility supply, or hardware that accepts a higher inlet. Each changes something else in the design. None should be chosen merely to make the quotation spreadsheet look consistent.

These temperatures are illustrative. Use actual supported limits and selected equipment performance rather than treating 5°C as a universal good-design target.

Does a lower approach always save money?

Not automatically. It may help the facility operate with warmer water or increase heat-rejection options, but achieving it can affect heat-exchanger size, flows, pumping and capital cost. Evaluate the complete system and operating hours.

The CDU 100 application and planning guide includes performance information across approach and facility conditions. Product-specific curves are more useful here than a generic “high efficiency” description.

Also ask how the selection accommodates fouling assumptions, fluid changes and maintenance. A clean nominal selection should not be mistaken for a commitment under every future condition.

What should commissioning verify?

Use identified sensor locations and calibrated measurements to record both loops' entering and leaving temperatures, flow and transferred load. Confirm whether the observed duty matches the agreed test condition before judging the approach figure.

File that result with the acceptance criteria. Our flow-rate calculation guide covers the heat balance, while the CDU overview explains the wider control and isolation functions.

Sources & further reading

Use the manufacturer’s instructions for your exact equipment. Read our editorial policy or suggest a factual correction.

Explore the company directory → · All liquid-cooling guides →

01
Data centers

45°C AI Cooling: When Can a Data Center Skip Chillers?

Understand 45°C AI cooling, dry-cooler and CDU temperature budgets, and why chiller-less operation depends on supported hardware and local conditions.

↗
02
Data centers

Does Liquid Cooling Waste Water? Follow the Whole Cooling System

Water circulating inside a server loop is not the same as water evaporating outside. Learn how to read water-use claims without confusing the two.

↗
03
Buying guides

Glycol Chiller Sizing for Fermentation and Cold Crash

Estimate fermentation and cold-crash cooling loads, compare capacity at actual conditions, and separate reservoir storage from continuous chiller output.

↗

Directory matches are starting points for research. Confirm product fit and availability with the company.