US Liquid Cooling editorial · Reviewed · 4 min read
Spray liquid cooling and immersion cooling can both bring dielectric fluid into contact with IT hardware, but they distribute that fluid differently. In a spray design, fluid is directed toward selected surfaces or assemblies. In an immersion design, hardware operates within a body of cooling fluid.
Neither label tells you the complete facility requirements. You still need to establish heat rejection, fluid management, hardware compatibility and the service procedure.
Why is spray cooling appearing in the current discussion?
In an October 5, 2026 announcement, AIRSYS and Shell described a spray-cooling demonstration planned for the OCP Global Summit period. AIRSYS positioned its cassette-based architecture for retrofit, edge and mid-density AI applications.
That announcement is evidence of current supplier activity, not an independent comparison of all spray and immersion products. The useful next step is to ask what the proposed architecture changes for a particular deployment.
For operators evaluating several routes beyond conventional air cooling, spray systems deserve a defined technical review rather than being grouped into “immersion” without further detail.
Compare where the fluid goes
With immersion, the system is designed around hardware operating in dielectric fluid. In single-phase immersion, the liquid carries heat without intentionally boiling; two-phase immersion adds a different heat-transfer and condensation process.
Shell's single-phase immersion explanation provides one manufacturer description of the single-phase approach.
For a spray system, ask which components receive fluid, how distribution is maintained across operating conditions, where fluid collects and how heat leaves the enclosure. Also establish whether the proposed product is single-phase or uses phase change. The word “spray” alone does not settle that question.
Fluid inventory is only one comparison
A smaller fluid inventory can change fill, handling and service logistics. It does not establish total operating cost or reliability by itself.
Compare the systems at the same useful heat duty and boundary. Include pumps, fans or facility equipment, heat exchangers, filtration and any remaining air-side cooling. Check whether the quoted fluid amount includes reservoirs, pipework and service stock.
Do not compare a server cassette's inventory with the entire fluid inventory of a much larger installation and treat the difference as an architectural performance result.
Ask how a server is serviced
Walk through a realistic replacement task with the supplier. Which connections are isolated? Is the server drained, lifted, wiped or cleaned? How much fluid remains on the hardware? What tools, lifting arrangements and trained staff are required?
| Service question | Evidence to request |
|---|---|
| Time to remove a failed component | Demonstrated procedure and stated starting condition |
| Fluid exposure during maintenance | Handling instructions and compatible protective equipment |
| Return to service | Checks for connections, fluid condition and cooling performance |
| Spare-part replacement | Exact compatible parts and cleaning requirements |
| Warranty | Written scope for server, tank or cassette, and fluid |
A serviceable demonstration model is useful, but ask to see the procedure for the production configuration you intend to buy.
Compatibility remains a system-level question
Dielectric behavior does not mean a fluid is harmless to every plastic, adhesive, connector or cable. Hardware originally designed for air may need changes or explicit approval before direct fluid contact.
The OCP immersion-cooling community maintains work on material compatibility, fluids and warranty guidance. Those are relevant evaluation topics wherever dielectric liquid directly contacts electronics, even when the fluid-delivery method differs.
Ask the spray-system vendor which evidence is specific to its operating conditions. A compatibility result from another immersion system may be informative without being sufficient approval.
What would a useful pilot measure?
Agree the workload, ambient conditions, cooling boundary, captured heat, auxiliary electricity, fluid inventory and service tasks before testing. Include an approved fault-response demonstration and condition checks after the test period.
Use those results to compare the candidate with your site's alternatives. A pilot should answer whether the system meets your requirements, not simply produce a low chip-temperature screenshot.
For the broader architecture choice, see direct-to-chip versus immersion cooling. For comparing measured outcomes, use clear energy and water reporting boundaries.
Sources & further reading
- Airsys and Shell Showcase Spray Liquid Cooling for Data Centers at OCP Global Summit - AIRSYS North America ↗
- single-phase immersion explanation ↗
- immersion-cooling community ↗
Explore the company directory → · All liquid-cooling guides →